Projets
Champlain Bridge barge
Mandate
Fast delivery of equipment for our client
As part of our time-critical mandate, we provided submersible pumps to meet filling and draining requirements. Our goal was to ensure a 4-hour refill time and a quick drain, within a 30–60 minutes window.
- 18 Tsurumi pumps
- 16 Benshaw starters
- 2 variable speed ABB starters
Details
Strengths
1,500 m3 of water discharged in 30 minutes
Robust and efficient pumps
Fast shipping
11 shipments organized by our team in collaboration with our Boucherville colleagues.
Challenges
Tight deadlines
9 weeks between initial equipment sizing works and commissioning.
Gallery